Timings

How long does it take to install solar panels?

The answer depends on which clock you mean. The work on your roof is quick. The time from first enquiry to a system that's certified and earning export payments is much longer, and most of it is paperwork, ordering and waiting for approvals.

Checked at source on 3 November 2026 · Published by SEO-DONS LTD

The stages

Where the time goes

Typical order of events; actual times depend on the installer, the season and your network operator
StageWhat happensWhat decides how long
SurveyA visit to look at the roof, wiring and meterThe installer's diary; your availability
QuotesWritten quotes and estimates arriveHow many you ask for; RECC recommends three
Contract and cancellationYou sign; a 14-day cancellation period may applyWhether you signed at home, online or on the firm's premises
Design and orderingFinal design; equipment orderedStock and the installer's workload
Network approvalG99 application, if the system is above 16 A per phaseThe network operator's response time
InstallationScaffolding, panels, wiring, inverter, testingRoof complexity; weather; any battery
PaperworkMCS certificate and other documentsWithin 30 days of completion

On the day

The installation itself

For a straightforward roof, the work on site usually takes a day or two. Scaffolding often goes up beforehand and comes down afterwards, so it may be in place for longer than the installers are. The order is typically: mounting rails fixed to the rafters, panels placed and wired, cable run to the inverter, isolators and protection fitted, connection to the consumer unit, generation meter, then testing and commissioning.

Things that add time: a complicated roof with several faces or valleys, in-roof rather than on-roof mounting, a battery, a consumer unit that needs upgrading, or poor weather, since roof work stops in high winds and heavy rain. Your installer should tell you in advance what access they need, and agree it with you.

Before the day

Why there's a gap after you sign

Several things have to happen between signing and installation. The installer completes the detailed design, which may differ from the quote; if it changes significantly, the MCS Customer Commitment says you must be given a written variation and the choice to cancel. Equipment is ordered. Scaffolding is booked. And for systems above 16 A per phase, the installer applies to the network operator under G99 and waits for approval before work can start.

If you signed at home or online, there's also the cancellation period. Under the Consumer Contracts Regulations, for a service contract it normally ends 14 days after the day the contract is made. Work can start sooner only if you ask in writing, and if you then cancel, you may have to pay for work done.

Delays

What an installer must tell you about timing

The MCS Customer Commitment asks installers to tell you how long the installation will take and agree a timeline with you, to let you know about any delays, to advise estimated delivery and installation dates, and to keep you updated before, during and after the work. If the dates change significantly from the contract, that's a change you should be told about in writing.

Delays happen: equipment shortages, network approvals, weather. What matters is that you're told. A firm that goes quiet after taking a deposit is a reason to act. See when something goes wrong.

Speed as a sales tactic

Be wary of "we can fit you next week"

Speed isn't a bad thing in itself, but a promise of very quick installation can be a sign that a survey is being skipped, that a G99 application hasn't been considered, or that the firm wants you committed before you've compared quotes. RECC warns against pushy tactics and discounts for signing on the spot.

A realistic timeline, explained step by step, is a better sign than a fast one. See the process step by step and red flags.

After the day

When the system is really finished

A system that's been switched on isn't quite finished. The handover should include a demonstration and a pack of documents. Within 30 calendar days of completion, the installer must give you the MCS certificate, any building regulations compliance certificate and proof of network notification or approval where it was needed. Only then can you apply for export payments with everything in hand.

If any of those documents haven't arrived by day 30, ask for them in writing. See maintenance and aftercare.

Quick answers

Timing questions

How long does solar panel installation take?

On site, usually a day or two for a typical home once scaffolding is up. From first survey to a working system, allow several weeks, longer if a G99 application is needed.

Why is there a wait between signing and installation?

Detailed design, ordering equipment, booking scaffolding, any network application, and any cancellation period all fall between signing and installation.

When will I get the MCS certificate?

Within 30 calendar days of completion, under the MCS Customer Commitment, together with any building regulations certificate and proof of network notification.

Can installation start before the cancellation period ends?

Only if you ask for it in writing. If you then cancel, you may have to pay for work already done.

Planning your diary

When you'll need to be around

You'll want to be home for the survey, so you can answer questions about your use and show the surveyor the loft, the fuse board and the meter. On installation day someone needs to give access and be there at the end for the handover, when the installer demonstrates the system and goes through the pack. Between those, most of the work is the installer's, though you may be asked to confirm details for a network application.

Sources for this page

Ready for a solar panel quote?

Tell us about the house and the roof, and what you would like priced: panels, a battery or both. If an installer has already quoted, add the system size and the price. Your details reach SEO-DONS LTD, which runs Solar Panel Installers, and we reply by email.

What happens next

  1. Your details go to SEO-DONS LTD, the company that runs Solar Panel Installers.
  2. We read what you have told us about the house and reply by email.
  3. Asking for a quote costs nothing and puts you under no obligation.
Add more about the house, or a quote you hold (optional)

Published by SEO Dons Ltd. We don't install panels ourselves. We reply by email. See our privacy notice.

Get a solar quote
Get a solar quote