Network notification
Do you need network operator permission for solar panels?
Every home solar system connects to the local electricity network, and the company that runs that network, the distribution network operator or DNO, has to know about it. Whether that's a simple notification or an application depends on the size of the system.
Checked at source on 3 November 2026 · Published by SEO-DONS LTD
The law
Why the network operator has to know
The Electricity Safety, Quality and Continuity Regulations 2002 set the rules for generators that run in parallel with the public network, which is what a grid-connected solar system does. Regulation 22 requires, among other things, that the network operator is told of the intention to run such a source before or at the time it is commissioned, and that the system disconnects automatically if the network fails, so that it can't feed power into lines engineers believe are dead.
Smaller sources, at 16 A per phase or less at low voltage, are exempt from some of the other conditions, but not from telling the operator. That threshold is what separates the two routes in practice.
The engineering recommendations that set out the process are known as G98 and G99, after the documents published by the Energy Networks Association.
The two routes
G98: notify after. G99: apply before.
G98 covers small generators up to and including 16 A per phase. On a typical single-phase home that is about 3.68 kW of inverter output. The installer fits the system and then notifies the network operator within 28 days. Many smaller home solar systems fall into this route.
G99 covers anything bigger. The installer applies to the network operator before installation, with details of the system, and waits for a decision. The operator may approve it as proposed, approve it with conditions such as an export limit, or ask for changes. That takes time, so ask early whether your system will need it.
MCS's guidance for installers notes that panels and a battery on the same connection add together, and that the combination will often exceed 16 A per phase. A system that would be G98 on its own can become G99 when a battery is added.
Side by side
G98 and G99 compared
| G98 | G99 | |
|---|---|---|
| Covers | Up to and including 16 A per phase (about 3.68 kW single-phase) | Above 16 A per phase |
| When | Notify within 28 days of installation | Apply and get approval before installation |
| Can it be refused or limited? | It is a notification | It can be approved with conditions, such as an export limit |
| Effect on timing | None before installation | Can add weeks while the operator decides |
| Who does it | Normally the installer; proof to you within 30 days of completion under the MCS Customer Commitment | |
What to ask
Questions for your installer about the network
- Which route does my system need, G98 or G99, and why?
- If G99, when will you apply, and how long do you expect it to take?
- Is there any chance of an export limit, and how would it affect the performance estimate?
- If I add a battery later, will that need a new application?
- Will you send me proof of notification or approval?
The MCS Customer Commitment requires installers to tell you all the permissions, approvals and licences needed before you sign, and to give you proof of network notification or approval, where needed, within 30 days of completion.
Why it matters to you
Notification, exports and your paperwork
A system that hasn't been properly notified is a problem waiting to happen: for safety, for insurance, and when you sell the home. Export payments also depend on a certified, properly connected installation. Under the SEG, exports must be metered, and suppliers ask for the MCS certificate.
If an export limit is applied under G99, it caps what you can send to the grid at any moment. That can change the export side of a performance estimate, so ask for the estimate to reflect any limit.
Keep the network paperwork with the MCS certificate. See maintenance and aftercare and the process step by step.
Who the operators are
Your network operator
Great Britain is divided into regions, each served by a distribution network operator that owns and runs the local poles, cables and substations. It isn't your energy supplier: you choose a supplier, but your network operator depends on where you live, and it doesn't change if you switch supplier. Your installer will know which one covers your home and how its application process works.
You don't normally need to contact the operator yourself. If you're told a G99 application is under way, it's reasonable to ask for its reference and the date it was submitted, so you can follow its progress.
Network questions
Do I need DNO permission for solar panels?
The network operator must always be told. For small systems, up to 16 A per phase, that is a notification under G98 within 28 days. Larger systems need a G99 application and approval before installation.
Who applies to the DNO?
Normally your installer. The MCS Customer Commitment requires the installer to give you proof of notification or approval within 30 days of completion, where it is needed.
Does adding a battery change things?
Often. Panels and a battery on the same connection add together, and MCS notes the combination will often exceed 16 A per phase, which means a G99 application.
Can the network operator limit my system?
Under G99 it can approve the connection with conditions, such as a limit on how much can be exported. Ask your installer what was approved.
Later changes
If you change the system later
The notification describes the system as installed. Adding panels, swapping the inverter for a larger one or adding a battery can change what the network operator needs to know, and may move the system from G98 to G99. Ask the installer doing the later work to confirm which route applies before it starts.
Sources for this page
- legislation.gov.uk — ESQCR 2002, regulation 22 (generation in parallel with the network) read 3 November 2026
- MCS — guidance on notifying network operators (G98 and G99) read 3 November 2026
- MCS — The MCS Customer Commitment, version 1.1 (8 September 2026) read 3 November 2026
- Ofgem — SEG guidance for generators (PDF) read 2 November 2026
Ready for a solar panel quote?
Tell us about the house and the roof, and what you would like priced: panels, a battery or both. If an installer has already quoted, add the system size and the price. Your details reach SEO-DONS LTD, which runs Solar Panel Installers, and we reply by email.
What happens next
- Your details go to SEO-DONS LTD, the company that runs Solar Panel Installers.
- We read what you have told us about the house and reply by email.
- Asking for a quote costs nothing and puts you under no obligation.